Demolish existing jetty, build new jetty using turpentine piles and durability 1 hardwood superstructure. Client: MAST Date completed: Under construction Description of works: $1.3M Details of Innovations and extra value for money: We were able to offer turpentine piles at the some cost of treated Tassie hardwood piles. The turpentine piles last...

Demolish part of old wharf and build new dolphin consisting of 5, 450 x 12.7 steel piles, and concrete head. Client: Nyrstar Date completed: Feb 2011 Description of works: $240,000 Details of Innovations and extra value for money: TMC was able to spin piles 4m into the underlying rock then drill down...

Build new jetty and hydraulic gangway, demolish old jetty. Piles installed into solid rock, onsite fabrication blasting and painting. Client: Port Arthur Historic Site Management Date completed: Sep 2011 Description of works: $600,000 Details of Innovations and extra value for money: We were able to keep the existing jetty open for most...

Demolition of existing wharf and construction of 80m retaining wall type wharf. Drive 21no 400 CHS piles up to 20m long within 25mm position tolerance. Dredging 800 tonnes of material out of the river. Installation of 18no 13 tonne precast panels. Timber works, concrete cast...

Replacement of Southport wharf with concrete and steel structure. Designed by GHD, 60 x  400 diameter steel piles with poly sleeves, precast headstocks and precast planks. Structure is 120m long with 3.6 wide jetty and 11m wide wharf out the end. Client: Marine and Safety Tasmania Date completed: April...

Construction of new boardwalk including piling works, precast concrete supple and install, cast in situ concrete, earthworks, plastic decking, corten steel, architectural pavement slabs and electrical work. Client: Clarence city council Date completed: April 2010 Description of works: $1.7M Details of Innovations and extra value for money: We were able to spin...

Demolish old jetty and build new jetty out of Steel and concrete. Jetty also had a floating pontoon with aluminium gangway by Bellingham Marine Client: Marine and Safety Tasmania Date completed: September 2009 Description of works: $470,000 Details of Innovations and extra value for money: TMC was able to offer a very...

Construction of new jetty with hydraulic controlled gangway, fender dolphins and intermediate landing Client: Morilla Museum of Old and New art MONA Date completed: September 2009 Description of works: $340,000 Details of Innovations and extra value for money: TMC was able to offer the client significant savings and improving the aesthetics of...

Demolish old jetty and build new jetty, re shape/ armour groyne and pavement work. Client: Parks and Wildlife Date completed: Nov  2009 Description of works: $890k Details of Innovations and extra value for money: TMC was able to spin piles into the granite bedrock to enable the new wharf to be built...

Demolish old jetty and build new jetty using steel and concrete including a full length concrete wave wall Client: Marine and Safety Tasmania Date completed: Oct 2011 Description of works: $1M Details of Innovations and extra value for money: Despite horrendous weather conditions over winter we were able to deliver the project...