Projects

Demolition of existing wharf and construction of 80m retaining wall type wharf. Drive 21no 400 CHS piles up to 20m long within 25mm position tolerance. Dredging 800 tonnes of material out of the river. Installation of 18no 13 tonne precast panels. Timber works, concrete cast...

Replacement of Southport wharf with concrete and steel structure. Designed by GHD, 60 x  400 diameter steel piles with poly sleeves, precast headstocks and precast planks. Structure is 120m long with 3.6 wide jetty and 11m wide wharf out the end. Client: Marine and Safety Tasmania Date completed: April...

Construction of new boardwalk including piling works, precast concrete supple and install, cast in situ concrete, earthworks, plastic decking, corten steel, architectural pavement slabs and electrical work. Client: Clarence city council Date completed: April 2010 Description of works: $1.7M Details of Innovations and extra value for money: We were able to spin...

Demolish old jetty and build new jetty out of Steel and concrete. Jetty also had a floating pontoon with aluminium gangway by Bellingham Marine Client: Marine and Safety Tasmania Date completed: September 2009 Description of works: $470,000 Details of Innovations and extra value for money: TMC was able to offer a very...

Construction of new jetty with hydraulic controlled gangway, fender dolphins and intermediate landing Client: Morilla Museum of Old and New art MONA Date completed: September 2009 Description of works: $340,000 Details of Innovations and extra value for money: TMC was able to offer the client significant savings and improving the aesthetics of...

Demolish old jetty and build new jetty, re shape/ armour groyne and pavement work. Client: Parks and Wildlife Date completed: Nov  2009 Description of works: $890k Details of Innovations and extra value for money: TMC was able to spin piles into the granite bedrock to enable the new wharf to be built...

Demolish old jetty and build new jetty using steel and concrete including a full length concrete wave wall Client: Marine and Safety Tasmania Date completed: Oct 2011 Description of works: $1M Details of Innovations and extra value for money: Despite horrendous weather conditions over winter we were able to deliver the project...

Two new wharfs on a green field site in Macquarie Harbour, west coast Client: Fairbrother Date completed: December  2014 Description of works: $3.4M Details of Innovations and extra value for money: We were able to offer a redesign of the tendered design and saved the client around 2M. Client Contact:Mr John Cornell -...

Jetty demolition and replacement with reinforced concrete structure. New fenders, bollards, curbs ladders services. Client: Marine and Safety Tasmania Date completed: March 2015 Description of works: $2.1M Details of Innovations and extra value for money: MAST had relatively recently rebuilt parts of the deck so there was some sound re-usable timber in...