Splice 508 x 22mm wall piles to 27m long weighing over 6ton each.

Deliver to piling barge with dumb barge.

Pitch and drive to refusal.

On water extensions, handle and fit poly sleeves.

We are also doing demolition and dredging with another barge at the same time directly for the marina owner.

Client: Pacific Pontoon 
Date completed: Under construction
Cost of works: $500k

Details of and innovation or extra value for money:

We were able to mobilise quickly when the previous sub-contractor let them down. We have exceeded their program and are doing 3-4 pile per day.

Client Contact: Will Hatting (PPP) - 0467811000