Our projects span a wide range of marine and civil works, reflecting the expertise of our team, the trust of our clients, and our commitment to quality, safety, and lasting impact.
Following the successful completion of the temporary works, Tas Marine was awarded the contract to deliver the full Bellerive Stormwater Upgrade — the City of Clarence’s largest infrastructure project to date.
The upgrade involved constructing a sheet pile cofferdam across Bellerive Beach to enable trench excavation for the new sewer outfall. Tas Marine mobilised its jack-up barge with a 22t excavator for seaward dredging, alongside a 26t excavator with a sheet pile vibrator on the land side. More than 200t of sheet piles and steel struts were installed to form the temporary structure, which was removed once the outfall pile was completed.
Now fully operational, the new stormwater system at Beach Street significantly reduces flood risk to surrounding roads and properties during heavy rainfall.
Tas Marine is proud to have delivered this critical project with a strong focus on protecting the local environment and community. Working closely with the City of Clarence and stakeholders, the team implemented strict environmental protocols to minimise disruption to the marine environment, safeguard coastal ecosystems, support long-term sustainability goals for the region, and build greater resilience for the community.
Following the successful completion of the temporary works, Tas Marine was awarded the contract to deliver the full Bellerive Stormwater Upgrade — the City of Clarence’s largest infrastructure project to date.
The upgrade involved constructing a sheet pile cofferdam across Bellerive Beach to enable trench excavation for the new sewer outfall. Tas Marine mobilised its jack-up barge with a 22t excavator for seaward dredging, alongside a 26t excavator with a sheet pile vibrator on the land side. More than 200t of sheet piles and steel struts were installed to form the temporary structure, which was removed once the outfall pile was completed.
Now fully operational, the new stormwater system at Beach Street significantly reduces flood risk to surrounding roads and properties during heavy rainfall.
Tas Marine is proud to have delivered this critical project with a strong focus on protecting the local environment and community. Working closely with the City of Clarence and stakeholders, the team implemented strict environmental protocols to minimise disruption to the marine environment, safeguard coastal ecosystems, support long-term sustainability goals for the region, and build greater resilience for the community.
Tas Marine was contracted to deliver the temporary works for the Bellerive Stormwater Outfall. A sheet pile cofferdam was installed to enable safe excavation of a trench across Bellerive Beach for the new sewer outfall.
The works involved mobilising Tas Marine’s small jack-up barge with a 22t excavator for seaward dredging, alongside a 26t excavator with a sheet pile vibrator on the land side. In total, 200t of sheet piles and steel struts were used to form the temporary structure, which was successfully removed just one week after the outfall pile was installed.
Tas Marine was contracted to deliver the temporary works for the Bellerive Stormwater Outfall. A sheet pile cofferdam was installed to enable safe excavation of a trench across Bellerive Beach for the new sewer outfall.
The works involved mobilising Tas Marine’s small jack-up barge with a 22t excavator for seaward dredging, alongside a 26t excavator with a sheet pile vibrator on the land side. In total, 200t of sheet piles and steel struts were used to form the temporary structure, which was successfully removed just one week after the outfall pile was installed.
Tas Marine Construction has been contracted to deliver a 200-metre long break wall at Williamstown.
The combination wall design consists of 16mm sheet piles with rock-socketed piles installed at every second sheet. With challenging hard basalt ground conditions, Tas Marine is applying its specialist hard rock drilling expertise to drill and concrete the piles into position. Completion is scheduled for late 2025.
Tas Marine Construction has been contracted to deliver a 200-metre long break wall at Williamstown.
The combination wall design consists of 16mm sheet piles with rock-socketed piles installed at every second sheet. With challenging hard basalt ground conditions, Tas Marine is applying its specialist hard rock drilling expertise to drill and concrete the piles into position. Completion is scheduled for late 2025.
Tas Marine Construction was awarded the competitive tender to replace the Royal Yacht Club of Victoria’s aging travel lift jetties.
Works include demolition of the existing jetties, installation of new piles, and the supply and fit of steel superstructure and precast deck units. The project is progressing on schedule and will be completed ahead of the arrival of the new travel lift in mid-October.
Tas Marine Construction was awarded the competitive tender to replace the Royal Yacht Club of Victoria’s aging travel lift jetties.
Works include demolition of the existing jetties, installation of new piles, and the supply and fit of steel superstructure and precast deck units. The project is progressing on schedule and will be completed ahead of the arrival of the new travel lift in mid-October.
Demolish part of old wharf and build new dolphin consisting of 5, 450 x 12.7 steel piles, and concrete head.
Demolish part of old wharf and build new dolphin consisting of 5, 450 x 12.7 steel piles, and concrete head.
Build new jetty and hydraulic gangway, demolish old jetty. Piles installed into solid rock, onsite fabrication blasting and painting.
Build new jetty and hydraulic gangway, demolish old jetty. Piles installed into solid rock, onsite fabrication blasting and painting.
Demolition of existing wharf and construction of 80m retaining wall type wharf. Drive 21no 400 CHS piles up to 20m long within 25mm position tolerance. Dredging 800 tonnes of material out of the river. Installation of 18no 13 tonne precast panels. Timber works, concrete cast insitu works. Installation of geofabric and fill. Compaction, sub base and asphalting.
Demolition of existing wharf and construction of 80m retaining wall type wharf. Drive 21no 400 CHS piles up to 20m long within 25mm position tolerance. Dredging 800 tonnes of material out of the river. Installation of 18no 13 tonne precast panels. Timber works, concrete cast insitu works. Installation of geofabric and fill. Compaction, sub base and asphalting.
Replacement of Southport wharf with concrete and steel structure. Designed by GHD, 60 x 400 diameter steel piles with poly sleeves, precast headstocks and precast planks. Structure is 120m long with 3.6 wide jetty and 11m wide wharf out the end.
Replacement of Southport wharf with concrete and steel structure. Designed by GHD, 60 x 400 diameter steel piles with poly sleeves, precast headstocks and precast planks. Structure is 120m long with 3.6 wide jetty and 11m wide wharf out the end.
Construction of new boardwalk including piling works, precast concrete supple and install, cast in situ concrete, earthworks, plastic decking, corten steel, architectural pavement slabs and electrical work.
Construction of new boardwalk including piling works, precast concrete supple and install, cast in situ concrete, earthworks, plastic decking, corten steel, architectural pavement slabs and electrical work.
Demolish old jetty and build new jetty out of Steel and concrete. Jetty also had a floating pontoon with aluminium gangway by Bellingham Marine
Demolish old jetty and build new jetty out of Steel and concrete. Jetty also had a floating pontoon with aluminium gangway by Bellingham Marine
Construction of new jetty with hydraulic controlled gangway, fender dolphins and intermediate landing
Construction of new jetty with hydraulic controlled gangway, fender dolphins and intermediate landing
Demolish old jetty and build new jetty, re shape/ armour groyne and pavement work.
Demolish old jetty and build new jetty, re shape/ armour groyne and pavement work.
Demolish old jetty and build new jetty using steel and concrete including a full length concrete wave wall
Demolish old jetty and build new jetty using steel and concrete including a full length concrete wave wall
Two new wharfs on a green field site in Macquarie Harbour, west coast
Two new wharfs on a green field site in Macquarie Harbour, west coast
Replace timber jetty with concrete wave panels with reinforced concrete jetty and new wave panels. New wave panels were 4m deep and were supported on two rows of heavy steel UC’s bolted back to the piles. Difficult logistics of building a large structure 10 NM off shore from the east coast. Very exposed site to prevailing westerlies made construction difficult.
Replace timber jetty with concrete wave panels with reinforced concrete jetty and new wave panels. New wave panels were 4m deep and were supported on two rows of heavy steel UC’s bolted back to the piles. Difficult logistics of building a large structure 10 NM off shore from the east coast. Very exposed site to prevailing westerlies made construction difficult.
Jetty demolition and replacement with reinforced concrete structure. New fenders, bollards, curbs ladders services.
Jetty demolition and replacement with reinforced concrete structure. New fenders, bollards, curbs ladders services.
Off-site manufacture and installation of moving footbridge across the BYC slipway. There were two sets of hydraulic gates which open and shut to close the bridge off to pedestrian traffic then the bridge rolls back into a recess to open up the span. The whole system is electric over hydraulic. Fabrication by Saunders and Ward
Off-site manufacture and installation of moving footbridge across the BYC slipway. There were two sets of hydraulic gates which open and shut to close the bridge off to pedestrian traffic then the bridge rolls back into a recess to open up the span. The whole system is electric over hydraulic. Fabrication by Saunders and Ward
Demolish old timber deck, design and construct new RC concrete decks.
Mobilise to site, demolish old timber deck and fit new concrete decks
Demolish old timber deck, design and construct new RC concrete decks.
Mobilise to site, demolish old timber deck and fit new concrete decks
Build new bridge in virgin location between two golf clubs in Tasmania’s north east coast. Client had purchased second hand bridge decks and we were given the design and construct contract. The bridge was 70m long and 4.2m wide.
Build new bridge in virgin location between two golf clubs in Tasmania’s north east coast. Client had purchased second hand bridge decks and we were given the design and construct contract. The bridge was 70m long and 4.2m wide.
Demolish existing jetty, build new jetty using turpentine piles and durability 1 hardwood superstructure.
Demolish existing jetty, build new jetty using turpentine piles and durability 1 hardwood superstructure.
Jetty extension at Christmas Island in the Indian Ocean. Transport all plant and materials out to the Island, drive piles, some of which went 56m into the ground before they reached capacity. All site fabricated heavy steel sections, paint system and denso steelcoat 400 corrosion protection. Big lower landing built in the tide zone of a very exposed location.
Jetty extension at Christmas Island in the Indian Ocean. Transport all plant and materials out to the Island, drive piles, some of which went 56m into the ground before they reached capacity. All site fabricated heavy steel sections, paint system and denso steelcoat 400 corrosion protection. Big lower landing built in the tide zone of a very exposed location.
240m long piles break-wall. Average 10m water depth, painted steel steel piles driven, precast headstocks, concrete pour. 13t precast wave panels and underwater bolted connections.
240m long piles break-wall. Average 10m water depth, painted steel steel piles driven, precast headstocks, concrete pour. 13t precast wave panels and underwater bolted connections.
Demolish existing slipway and rebuild including a 30m extension into deeper water to enable the launching of a 1000t vessel
Demolish existing slipway and rebuild including a 30m extension into deeper water to enable the launching of a 1000t vessel
Two 5 x 5 m concrete dolphins on 6 piles each. Down the hole hammer drilling of all piles, Tension testing to 40t
Two 5 x 5 m concrete dolphins on 6 piles each. Down the hole hammer drilling of all piles, Tension testing to 40t
Drive 20 piles, most on 60 degree rake, construct 4m x 4m headstocks 2m underwater using coffer dam. 300t of precast elements
including some 35t
Drive 20 piles, most on 60 degree rake, construct 4m x 4m headstocks 2m underwater using coffer dam. 300t of precast elements
including some 35t
Re-build existing boat-ramp. Demolish old concrete steps, Drive turpentine piles for footing on new precast walls. Cut piles off and cast underwater beam on top of piles, completely encasing them in the beam. Fit precast up to 10t and pour topping slab on top
Re-build existing boat-ramp. Demolish old concrete steps, Drive turpentine piles for footing on new precast walls. Cut piles off and cast underwater beam on top of piles, completely encasing them in the beam. Fit precast up to 10t and pour topping slab on top
TMC pulled all the stops out to get MASTs Woodbridge Jetty open for Christmas with the fenders only arriving air freight one week prior. It was all hands on deck to fit the precast elements, fenders and lower landing in two weeks!” The concrete jetty is 195m2 and has a lower landing stage on either side.
TMC pulled all the stops out to get MASTs Woodbridge Jetty open for Christmas with the fenders only arriving air freight one week prior. It was all hands on deck to fit the precast elements, fenders and lower landing in two weeks!” The concrete jetty is 195m2 and has a lower landing stage on either side.
Replace and enhance boat ramp and jetty after damage in 2016 storms. TMC completed the new Parks & Wildlife Fortescue Bay boatramp in time for summer 2018. Walkways and bollards were added to the design to improve access for bushwalkers on the Three Capes Track.
Replace and enhance boat ramp and jetty after damage in 2016 storms. TMC completed the new Parks & Wildlife Fortescue Bay boatramp in time for summer 2018. Walkways and bollards were added to the design to improve access for bushwalkers on the Three Capes Track.
Demolition of existing concrete break-wall, fixed marina berths and piles.
Install new piles into rock including DTH drilling of piles into bluestone. Take delivery and assemble pontoons on water.
Demolition of existing concrete break-wall, fixed marina berths and piles.
Install new piles into rock including DTH drilling of piles into bluestone. Take delivery and assemble pontoons on water.
Install 50 piles into bluestone using DTH drilling gear. Piles had 610 driven casings, drilled sockets and RC concrete piles going into the bed rock.
Install 50 piles into bluestone using DTH drilling gear. Piles had 610 driven casings, drilled sockets and RC concrete piles going into the bed rock.
Take delivery of piles, welding of piles, handling and driving of piles
Take delivery of piles, welding of piles, handling and driving of piles
Construction of 500m long piled break-wall in up to 18m water depth. Precast wave panels are 8m deep weighing 25t. Total weight of structure 6000t.
Construction of 500m long piled break-wall in up to 18m water depth. Precast wave panels are 8m deep weighing 25t. Total weight of structure 6000t.
New 150m long pier on greenfield site
Pier had 20t concrete wave panels on one side to create a breakwall.
New 150m long pier on greenfield site
Pier had 20t concrete wave panels on one side to create a breakwall.
Excavating materials form port and marina to improve draft for berths and access into the port.
Materil was a mixture of mud, sand, loose rock and sandstone bedrock. The hard sandstone bed rock had to be broken with a rock-breaker operating underwater before it could be dug out.
Material was stockpiles in the carpark and allowed to dry. The council is planning on using the dredged material for land reclamation elsewhere in Triabunna shortly.
Excavating materials form port and marina to improve draft for berths and access into the port.
Materil was a mixture of mud, sand, loose rock and sandstone bedrock. The hard sandstone bed rock had to be broken with a rock-breaker operating underwater before it could be dug out.
Material was stockpiles in the carpark and allowed to dry. The council is planning on using the dredged material for land reclamation elsewhere in Triabunna shortly.
Design and construct a new rowing pontoon on a greenfield site.
Design and construct a new rowing pontoon on a greenfield site.
Supply and install steel piles with poly sleeves into rock.
Take delivery of pontoons and assemble on water.
Fit abutment and gangway. Install coverboard and buffer.
Supply and install steel piles with poly sleeves into rock.
Take delivery of pontoons and assemble on water.
Fit abutment and gangway. Install coverboard and buffer.
Looking to deliver your next marine or civil project with a trusted, experienced partner? We would love to hear from you – let’s talk about how we can support your next build.
Client: City of Clarence
Date Completed: May 2025
Description of works:
Tas Marine delivered Clarence City Council’s largest infrastructure project to date, including constructing a temporary sheet pile cofferdam across Bellerive Beach to enable excavation for a new stormwater outfall. Over 200 tonnes of steel were installed using specialised equipment. The new upgrade reduces flood risk to surrounding residential areas and supports long-term coastal resilience.
Client: Williamstown
Date Completed: Current
Total Contract Sum:
Description of works
Tas Marine Construction has been contracted to deliver a 200-metre long break wall at Williamstown.
The combination wall design consists of 16mm sheet piles with rock-socketed piles installed at every second sheet. With challenging hard basalt ground conditions, Tas Marine is applying its specialist hard rock drilling expertise to drill and concrete the piles into position. Completion is scheduled for late 2025.
Details of Innovations and extra value for money
Client Contact:
Client: Royal Yacht Club of Victoria
Date Completed: Current
Total Contract Sum:
Description of works
Tas Marine Construction was awarded the competitive tender to replace the Royal Yacht Club of Victoria’s aging travel lift jetties.
Works include demolition of the existing jetties, installation of new piles, and the supply and fit of steel superstructure and precast deck units. The project is progressing on schedule and will be completed ahead of the arrival of the new travel lift in mid-October.
Details of any Variations
Details of Innovations and extra value for money
Client Contact:
Date Completed: Current
Description of works
Construction of 500m long piled break-wall in up to 18m water depth. Precast wave panels are 8m deep weighing 25t. Total weight of structure 6000t.
Details of any Variations
Variations for additional PDA testing, pile lengths, pull out tests, acceleration and pile fins were approved and paid. Some painting was deleted and client was given a discount.