Projects

  • All
  • Bridges
  • Marinas
  • Marine Construction
  • Piling

Ship supplies from Australia. Splice 711 x 12.7 piles to 24m long. Handle onto piling barge, pitch and drive to finish level which was 1m below water. Handle and fit telescopic spiggots for connection of break-wall pontoons to piles. We also had to excavate out the inside...

Splice 508 x 22mm wall piles to 27m long weighing over 6ton each. Deliver to piling barge with dumb barge. Pitch and drive to refusal. On water extensions, handle and fit poly sleeves. We are also doing demolition and dredging with another barge at the same time directly for...

Demolish existing jetty, build two extra lanes on boat-ramp and re-place existing two lane boat-ramp. Extend existing Bellingham pontoon and supply and install new matching pontoon system on the other side. Client: Wellington Shire Council (Gippsland Vic)  Date completed: May 2018 Description of works: $1.1M Details of and innovation or extra value...

Demolish existing jetty, build new jetty using turpentine piles and durability 1 hardwood superstructure....

Demolish existing slipway and rebuild including a 30m extension into deeper water to enable the launching of a 1000t vessel. Client: Haywards Date completed: April 2017 Description of works: 890k  ...

Two 5 x 5 m concrete dolphins on 6 piles each. Down the hole hammer drilling of all piles, Tension testing to 40t Client: DSS Date completed: December 2017 Description of works: $1M Details of Innovations and extra value for money: We battled almost constant rain to build this over winter. Client Contact:Daryl...

Re-build existing boat-ramp. Demolish old concrete steps, Drive turpentine piles for footing on new precast walls. Cut piles off and cast underwater beam on top of piles, completely encasing them in the beam. Fit precast up to 10t and  pour topping slab on top Client: MAST Date completed: Under...

Demolish existing jetty, build new jetty using turpentine piles and durability 1 hardwood superstructure. Client: MAST Date completed: Under construction Description of works: $1.3M Details of Innovations and extra value for money: We were able to offer turpentine piles at the some cost of treated Tassie hardwood piles. The turpentine piles last...

Demolish part of old wharf and build new dolphin consisting of 5, 450 x 12.7 steel piles, and concrete head. Client: Nyrstar Date completed: Feb 2011 Description of works: $240,000 Details of Innovations and extra value for money: TMC was able to spin piles 4m into the underlying rock then drill down...

Build new jetty and hydraulic gangway, demolish old jetty. Piles installed into solid rock, onsite fabrication blasting and painting. Client: Port Arthur Historic Site Management Date completed: Sep 2011 Description of works: $600,000 Details of Innovations and extra value for money: We were able to keep the existing jetty open for most...